This is the property of the Daily Journal Corporation and fully protected by copyright. It is made available only to Daily Journal subscribers for personal or collaborative purposes and may not be distributed, reproduced, modified, stored or transferred without written permission. Please click "Reprint" to order presentation-ready copies to distribute to clients or use in commercial marketing materials or for permission to post on a website. and copyright (showing year of publication) at the bottom.

Contracts
Construction Contract
Delay

Zurn Constructors Inc. v. Castaic Lake Water Agency

Published: Nov. 7, 1998 | Result Date: Aug. 4, 1998 | Filing Date: Jan. 1, 1900 |

Case number: PC017718 Bench Verdict –  $0

Judge

Howard J. Schwab

Court

L.A. Superior San Fernando


Attorneys

Plaintiff

William R. Baerg

Patrick J. Duffy III


Defendant

J. Alberto Boada

R. Bruce Tepper Jr.


Experts

Plaintiff

Craig Sorensen
(technical)

Facts

In 1992, plaintiff Zurn Constructors Inc. contracted with defendant Castaic Lake Water Agency to build a water pipeline which connected the Metropolitan Water District's Foothill Feeder with defendant's new water treatment plant. The plaintiff completed construction seven months behind schedule, causing defendant to withold $411,000 in liquidated damages. The plaintiff filed suit for breach of contract.

Settlement Discussions

According to defendant, the plaintiff demanded $600,000, reduced to $470,000 during trial. The defendant made an offer of $200,000.

Damages

The plaintiff sought $570,663 in unpaid retention, extended overhead costs, and extra work claims.

Other Information

The verdict was reached approximately two years and two months after the case was filed. The plaintiff has filed a notice of appeal.

Length

10 days (bench trial)