This is the property of the Daily Journal Corporation and fully protected by copyright. It is made available only to Daily Journal subscribers for personal or collaborative purposes and may not be distributed, reproduced, modified, stored or transferred without written permission. Please click "Reprint" to order presentation-ready copies to distribute to clients or use in commercial marketing materials or for permission to post on a website. and copyright (showing year of publication) at the bottom.

CONFIDENTIAL

Nov. 28, 1998

Construction
Negligent Construction
Single Family Residence

Confidential

Settlement –  $410,000

Judge

Robert E. May

Court

San Diego Superior


Attorneys

Plaintiff

Andrew E. Berman


Defendant

John R. Clifford
(Wilson Elser Moskowitz Edelman & Dicker LLP)

Terry A. Pinnegar

Robert A. O'Connell Jr.


Experts

Plaintiff

Larry J. Gliko
(technical)

Bradford Baker
(technical)

Scott Thoeney
(technical)

Defendant

Mark D. Hetherington
(technical)

Wilmot F. Macklin III
(technical)

Richard English
(technical)

Daniel Steussy
(technical)

Steven A. Coolong
(technical)

Peter S. Curry
(technical)

John S. Rule
(technical)

Facts

The plaintiffs, owners of a single family residence, filed suit in San Diego against the general contractor, concrete subcontractor and the pool subcontractor for alleged negligence arising out of soils movement and an inadequate slab that caused damage to the residence, pool and surrounding hardscape.

Settlement Discussions

Settlement discussions were not disclosed.

Damages

The plaintiffs claimed the cost of repair was $512,795.

Other Information

The settlement was reached approximately one year and 10 months after the case was filed. A mediation was held before Scott Markus, resulting in the reported settlement.