B&D Construction v. 14311 Ventura LLC
Published: Dec. 1, 2023 | Result Date: Oct. 12, 2023 | Filing Date: Jul. 11, 2019 |Case number: 19VECV00980 Settlement – $250,000
Judge
Court
Los Angeles County Superior Court
Attorneys
Cross-Complainant
Ali Salamirad
(SMTD Law LLP)
Cross-Defendant
Robert F. Schauer
(Law Offices of Robert F. Schauer)
Facts
This case arose from an agreement between contractor B&D Construction and the developer of the Whole Foods in Sherman Oaks for removing contaminated soils.
Contractor alleged to be owed additional compensation when contaminated soils exceeded the initial project estimates.
Developer alleged that the contractor failed to prove that additional contaminated soils were removed.
After Contractor rested its case, Developer filed a motion to dismiss based on alleged violations of the Contractor License Laws and a failure to prove a material breach of a construction contract.
Injuries
Contractor sought in excess of $1,500,000 for its unpaid invoices, prompt payment penalties, attorneys fees and costs.
Result
On the second to last day of a two-week bench trial, the parties agreed to resolve the dispute with a payment of $250,000 from the developer to the contractor.