This is the property of the Daily Journal Corporation and fully protected by copyright. It is made available only to Daily Journal subscribers for personal or collaborative purposes and may not be distributed, reproduced, modified, stored or transferred without written permission. Please click "Reprint" to order presentation-ready copies to distribute to clients or use in commercial marketing materials or for permission to post on a website. and copyright (showing year of publication) at the bottom.

CONFIDENTIAL

Nov. 1, 1997

Construction
Construction Defects
Condominium Complex

Confidential

Settlement –  $1,000,000

Judge

Ross Hart

Court

L.A. Superior Glendale


Attorneys

Plaintiff

David Swedelson

Matt D. Ober


Defendant

Joseph Gallo

Christopher Chapman


Facts

The defendant corporate developer contracted with defendant general contractor to build a 35-unit condominium complex in Montrose, California. The construction was completed in July 1989. Soon after construction was completed and the 35 units were sold, the homeowners experienced severe flooding and water intrusion throughout the complex and into the individual units. The plaintiff claimed that despite the developer and general contractor's repair attempts, the problems grew worse. Ultimately, the Association filed suit in May 1995 alleging damages from construction defects under various theories of recovery including strict liability, negligence, breach of warranty and breach of fiduciary duty. The plaintiff contended that the developer and general contractor failed to follow the building plans and specifications and local building codes in the design and construction of the condominium complex. The defendants cross-complained against various subcontractors for breach of express and implied warranties.

Settlement Discussions

The plaintiff's mediation settlement demand was $1.2 million. The defendants responded with an offer of $470,000.

Damages

The plaintiffs claimed damages from severe water intrusion and inadequate drainage including window leaks, roof leaks, flooding through first floor courtyard and walkways into units, warped and deteriorated wood siding and deteriorated elevated balconies, walkways and decks.

Other Information

The settlement was reached through mediation approximately one year and six months after the case was filed. A mediation was held in October 1996 before Ross R. Hart, of AAA, followed by a series of expert meetings and meetings among counsel for the parties. A final mediation session was held on March 5, 1997. A motivation for settlement in March was the prospect of obtaining settlement funds quickly and making repairs before additional rains. To ensure prompt payment of settlement contributions, the parties agreed to pay interest of 10 percent on all outstanding settlement payments to be paid by defendants. Final settlement funds were not collected until October 1997. According to defendants, a dispute arose regarding the interest payments. Finally, defendants paid an additional $8,000 to plaintiff.


#79828

For reprint rights or to order a copy of your photo:

Email jeremy@reprintpros.com for prices.
Direct dial: 949-702-5390