9th Circuit rejects challenge to Diablo Canyon exemption
The nuclear power plant had been scheduled to be decommissioned next year, but the state Legislature passed a bill, SB 846, in 2022 that approved Pacific Gas & Electric Co.'s continued use of the facility due to climate change and California's need for "carbon free electricity."




A 9th U.S. Circuit Court of Appeals panel on Monday denied a petition by several groups opposed to the Diablo Canyon nuclear power plant which argued that the U.S. Nuclear Regulatory Commission wrongly granted an exemption that allowed the plant to continue operating.
The plant had been scheduled to be decommissioned next year, but the state Legislature passed a bill, SB 846, in 2022 that approved Pacific Gas & Electric Co.'s continued use of the facility due to climate ch...
For only $95 a month (the price of 2 article purchases)
Receive unlimited article access and full access to our archives,
Daily Appellate Report, award winning columns, and our
Verdicts and Settlements.
Or
$795 for an entire year!
Or access this article for $45
(Purchase provides 7-day access to this article. Printing, posting or downloading is not allowed.)
Already a subscriber?
Sign In