This is the property of the Daily Journal Corporation and fully protected by copyright. It is made available only to Daily Journal subscribers for personal or collaborative purposes and may not be distributed, reproduced, modified, stored or transferred without written permission. Please click "Reprint" to order presentation-ready copies to distribute to clients or use in commercial marketing materials or for permission to post on a website. and copyright (showing year of publication) at the bottom.

Contracts
Breach of Contract
Construction Contracts

Michael Merino v. Chaffey Community College District

Published: May 27, 2006 | Result Date: Mar. 17, 2006 | Filing Date: Jan. 1, 1900 |

Case number: RCV067387 Settlement –  $325,000

Judge

Robert Cole

Court

San Bernardino Superior


Attorneys

Plaintiff

H. James Keathley
(Keathley & Keathley LLP)


Defendant

Victor L. Wolf
(Best, Best & Krieger LLP)


Facts

Merino and Chaffey entered into a contract whereby Merino agreed to design ADA (Americans with Disabilities Act) upgrades & HVAC upgrades to numerous campus buildings for 13.5 percent of the cost of the upgrades. Merino's drawings were completed and approved by the Department of State Architect. When Chaffey sent the project out for a construction bid, the winning bid was for $2,126,700. However, Chaffey used a deductive alternative formula for the first time, which was not approved by the DSA, and selected only one part of the project to be constructed. Therefore, the project was not built by Chaffey in accordance with the DSA approved plans. Chaffey only paid Merino 13.5 percent of the $753,000 contract with the contractor.

Contentions

PLAINTIFF'S CONTENTIONS:
Merino claimed entitlement to 13.5 percent of the entire accepted bid of $2,126,700, which amounted to $287,104.50. Merino claimed Chaffey never told him prior to completion of all of the plans that Chaffey intended to only award a contract on a portion of the accepted bid. Merino did all the plans for the ADA/HVAC upgrades for approximately seven buildings at Chaffey, and obtained DSA approval of those plans. Chaffey could not have obtained any bids without all of the plans.

DEFENDANT'S CONTENTIONS:
Chaffey contended that it was only required to pay Merino 13.5 percent of the amount of the construction contract awarded, or $93,250, and that Merino had been fully paid.

Other Information

As part of the settlement, Merino has been substituted out as architect of record for the project. ________________ ________________ PLEASE PROVIDE THE FIRST NAME OF THE JUDGE ____________ COLE.


#118975

For reprint rights or to order a copy of your photo:

Email jeremy@reprintpros.com for prices.
Direct dial: 949-702-5390