This is the property of the Daily Journal Corporation and fully protected by copyright. It is made available only to Daily Journal subscribers for personal or collaborative purposes and may not be distributed, reproduced, modified, stored or transferred without written permission. Please click "Reprint" to order presentation-ready copies to distribute to clients or use in commercial marketing materials or for permission to post on a website. and copyright (showing year of publication) at the bottom.

Contracts
Construction Contract
Failure to Pay

Abraham Victor Ponce, sole owner of Ponce Company v. Philco Construction Inc. et al., and related cross-action

Published: Sep. 3, 2011 | Result Date: Jul. 5, 2011 | Filing Date: Jan. 1, 1900 |

Case number: RIC521704 Verdict –  $92,000

Court

Riverside Superior


Attorneys

Experts

Facts

Abraham Victor Ponce filed suit against the defendant because he was owed over $90,000 on his contract for completed work.

In the cross-complaint, defendant alleged that the contract was not paid in full because cosmetic issues with the concrete delayed the defendant's store opening, resulting in lost earnings.

After a four-week trial, the jury found in favor of Ponce. The subcontractor was awarded $92,000, plus 10 percent interest for the last two years of non-payment, and was found zero percent at fault for the construction defects.

Result

$92,000 for plaintiff/cross-defendant Ponce.

Length

four weeks


#89445